V
verossa
Hi
I've noted that if I go back to a task and try to change the hours MS
Project provides a warning "The resource is assigned outside the original
dates for task 1 ... blah blah in project. The duration of the
fixed-duration task will change to accommodate the resource assigned."
In my project MS Project assigns resource automatically. Therefore, if a
fixed-duration task for a period of 1 day requires 16 hours MS Project will
assign 2.0 / 200%.
However, if I try to change the number of hours or if the actual working
time is greater, MS Project plays with the duration rather than the resource
allocation.
I'm sure this is a standard issue, and I should like (Steve suggests in my
previous post) know more about the resource on the project... But given the
task is fixed-duration, I would have assumed the resource allocation would
increase accordingly to ensure the completion date is not compromised.
I'm doing something wrong (again)?
TIA to all who replay - Vers
I've noted that if I go back to a task and try to change the hours MS
Project provides a warning "The resource is assigned outside the original
dates for task 1 ... blah blah in project. The duration of the
fixed-duration task will change to accommodate the resource assigned."
In my project MS Project assigns resource automatically. Therefore, if a
fixed-duration task for a period of 1 day requires 16 hours MS Project will
assign 2.0 / 200%.
However, if I try to change the number of hours or if the actual working
time is greater, MS Project plays with the duration rather than the resource
allocation.
I'm sure this is a standard issue, and I should like (Steve suggests in my
previous post) know more about the resource on the project... But given the
task is fixed-duration, I would have assumed the resource allocation would
increase accordingly to ensure the completion date is not compromised.
I'm doing something wrong (again)?
TIA to all who replay - Vers