M
Maha
I go into the emp and update teh task hours for example
I have two task
1. bake cookies
2. Bake Bread
Baker goes into his task and add that he worked 10 hours on bake cookies task
I go into update task and accept the hours
when I go into the project server view under budget and cost view I noticed
that not just the the bake cookies hours acutal adjust but also the bake
bread.
why would bake cookies actual change bake breads, they are not linked and
there are no predessors??
I have two task
1. bake cookies
2. Bake Bread
Baker goes into his task and add that he worked 10 hours on bake cookies task
I go into update task and accept the hours
when I go into the project server view under budget and cost view I noticed
that not just the the bake cookies hours acutal adjust but also the bake
bread.
why would bake cookies actual change bake breads, they are not linked and
there are no predessors??