C
chris.read-smith
I have a query here that doesnt quite add up for me. Hope someone out
there can help
Resources Work 38 hour weeks
Resources Work 7.6 hour days
Resource Rate $35 / hour
Status Date of Plan 13/12/2006
Status Date of Plan 31/10/2007
Task A
Start Date 29/10/07
Finish Date 16/01/08
Physical % Complete 100%
% Work Spent (Custom Field) 352%
Baseline Work 140hrs
Actual Work 493.75
BCWS (PV) $869.17
BCWP (EV) $4900
ACWP $869.17
SV $4030.83
SV% 463%
CV $4030.83
CV% 82%
CPI 5.64
SPI 5.64
How can the ACWP be the same as the BCWP yet we worked 352% more hours?
there can help
Resources Work 38 hour weeks
Resources Work 7.6 hour days
Resource Rate $35 / hour
Status Date of Plan 13/12/2006
Status Date of Plan 31/10/2007
Task A
Start Date 29/10/07
Finish Date 16/01/08
Physical % Complete 100%
% Work Spent (Custom Field) 352%
Baseline Work 140hrs
Actual Work 493.75
BCWS (PV) $869.17
BCWP (EV) $4900
ACWP $869.17
SV $4030.83
SV% 463%
CV $4030.83
CV% 82%
CPI 5.64
SPI 5.64
How can the ACWP be the same as the BCWP yet we worked 352% more hours?