J
Joe McCormack
I need four different calendars for my projects due to the use of shift work.
I am scheduling in a factory that can run as many as three shifts. My
standard is 8-5 for the office. For the fabrication shops I have created a
early 8 hour shift and an early 9 hour shift. I now need an early 10 hour
shift. If I start a new project and modify one of these calendars, I have
been told that by modifiy the calendar it will modify all projects with the
new information. Is that correct.
Thanks,
I am scheduling in a factory that can run as many as three shifts. My
standard is 8-5 for the office. For the fabrication shops I have created a
early 8 hour shift and an early 9 hour shift. I now need an early 10 hour
shift. If I start a new project and modify one of these calendars, I have
been told that by modifiy the calendar it will modify all projects with the
new information. Is that correct.
Thanks,