I'm tried to add a cost resource assignment on a task using PSI, project web
service. The assignment adn the value of the cost for this assign is
displayed correct in PWA (Assign cost view from project center). When i open
the project with Project Professional the value of the cost is 0.
Is there a way to assign costs to tasks from PSI ?
(As an workaround i used material resource instead of cost resource. But i
don't know if this is a good idea and what implications can have)