Dear All..
I have some problem, :
I was assigned task A (project X) for 4 hours in timesheet period
12/17/2007-12/21/2007
and task B (project Y) for 3hours in timesheet period 12/17/2007-12/21/2007

I have done task A in 12/17/2007 for 2hours and in 12/18/2007 for 2hours. I
have submitted the timesheet and sumbitted the task, so the task have percent
completed = 100 %. But I don't do the task B (project Y) in that week and I
will do it in next timesheet period

for the timesheet period 12/24/2007-12/28/2007, I do the the task B, because
it doesn't appear in this timesheet, so I must add line to get the task B in
timesheet.

My question : The task A (project X) which have percent competed = 100% and
have been approved my PM is still appear in task list if I try to add line
for task B (project Y). Can we set in order to the task A is doesn't appear
because it have been completed?

thx a lot ..i can join in this forum and get many knowledge and helping :)

Regard
 
P

Paul Conroy

You need to reschedule incomplete work and republish the project for task B
to automatically show in the following week.

Did you republish project x after accepting updates ?
 