Let's assume user1 is assigned to work on tasks t1 and t2 for a given
timesheet period.
But actually user1 has also worked on task t3 where he was not initially
assigned to and he/she 'd like to report time spent on said t3 within
Timesheet.
When user1 tries to "Add lines" he/she only sees the tasks assigned to
him/her? (by the wey, option "select from existing assignments" is checked)
Question 1: is it possible to enable user1 to see all the tasks of the
project he/she is involved in? If so how?
Question 2: how to uncheck option "select from existing assignments" ?
Question 3: Is-there specific rights to allow to see all project tasks?

Many thanks in advance for your precious help
jpa
 
R

reza

Dale--

Do you mean self-assign him/herself same with self assign team task??
when i click self-assign team task...there were nothing...there weren't any
task..just blank page.
can you give me more details about this??

thanks

reza
 
D

Dale Howard [MVP]

Reza --

No. Do not use the Self-Assign Team Task button. Click the New pick list
and then select Task. On the New Task page, the team member has the option
to assign him/herself to an existing task. Hope this helps.
 