J
jpa
Hi,
(PS2007, SP1, PIU)
Let's assume user1 is assigned to work on tasks t1 and t2 for a given
timesheet period.
But actually user1 has also worked on task t3 where he was not initially
assigned to and he/she 'd like to report time spent on said t3 within
Timesheet.
When user1 tries to "Add lines" he/she only sees the tasks assigned to
him/her? (by the wey, option "select from existing assignments" is checked)
Question 1: is it possible to enable user1 to see all the tasks of the
project he/she is involved in? If so how?
Question 2: how to uncheck option "select from existing assignments" ?
Question 3: Is-there specific rights to allow to see all project tasks?
Many thanks in advance for your precious help
jpa
(PS2007, SP1, PIU)
Let's assume user1 is assigned to work on tasks t1 and t2 for a given
timesheet period.
But actually user1 has also worked on task t3 where he was not initially
assigned to and he/she 'd like to report time spent on said t3 within
Timesheet.
When user1 tries to "Add lines" he/she only sees the tasks assigned to
him/her? (by the wey, option "select from existing assignments" is checked)
Question 1: is it possible to enable user1 to see all the tasks of the
project he/she is involved in? If so how?
Question 2: how to uncheck option "select from existing assignments" ?
Question 3: Is-there specific rights to allow to see all project tasks?
Many thanks in advance for your precious help