J
jpa
Hi
(PS2007, SP1 + PIU)
People are reporting time via Timesheet page.
I defined a "task level" custom field with lookup table (enabling to
categorize tasks types according to our company criteria).
So I'd like to build OLAP Cube Data Analysis report to know "time spent" per
"task type" from the "Timesheet" EPM cube: ie table like
-------------------------------------
Quater/month/weeks
task type: time spent
-------------------------------------
What are the steps to add "task type" custom field as dimension for
"timesheet" OLAP Cube?
I tried to add this custom filed as a cube dimension but dimension only
appears within "Task Non-Timephased" OLAP Cube..
Did-I missed something?
Am I using the right "timesheet" cube (among Timesheet, EPM Timesheet or
MSP_Project _Timesheet)
(Rules for adding new cube dimension are not so clear to me)
Thanks for your help
jpa
(PS2007, SP1 + PIU)
People are reporting time via Timesheet page.
I defined a "task level" custom field with lookup table (enabling to
categorize tasks types according to our company criteria).
So I'd like to build OLAP Cube Data Analysis report to know "time spent" per
"task type" from the "Timesheet" EPM cube: ie table like
-------------------------------------
Quater/month/weeks
task type: time spent
-------------------------------------
What are the steps to add "task type" custom field as dimension for
"timesheet" OLAP Cube?
I tried to add this custom filed as a cube dimension but dimension only
appears within "Task Non-Timephased" OLAP Cube..
Did-I missed something?
Am I using the right "timesheet" cube (among Timesheet, EPM Timesheet or
MSP_Project _Timesheet)
(Rules for adding new cube dimension are not so clear to me)
Thanks for your help
jpa