Add/Remove Fields to 'Timesheet' in the PWA

S

Shai R

Hi,

I am using MSP 2007 server, and this question regards the PWA.

I want the resource to report on his weekly tasks progress only using his
timesheet in the PWA - and then all his tasks will be updated in the Project
- is it possible?

Second option:
I want to add the field 'Remaining Work' to my Timesheet. In this way the
resource will add his tasks to the timesheet, report his actual work and also
the remaining work for each taks. In the final step, in 'My Tasks' the
resource will be able to import the relevant timesheet and all the tasks data
will be imported (without the need to enter the remaining work in 'My Tasks'
screen for each task - which can be 15-20 tasks per week).
The purpose of this option is that the resource will need to enter data only
in the 'Timesheets' section and not in 2 places.

Thanks in advance for any help on this,
Regards,

Shai
 
D

Dale Howard [MVP]

Shai --

Unfortunately, you cannot do everything you want with Project Server 2007.
First of all, the system does not allow you to add the Remaining Work column
to the My Timesheet page. You can add the Remaining Work field to the My
Tasks page, however. Team members can enter their time each day on the My
Timesheet page and then import the actual work on the My Tasks page. Hope
this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top