S
Shai R
Hi,
I am using MSP 2007 server, and this question regards the PWA.
I want the resource to report on his weekly tasks progress only using his
timesheet in the PWA - and then all his tasks will be updated in the Project
- is it possible?
Second option:
I want to add the field 'Remaining Work' to my Timesheet. In this way the
resource will add his tasks to the timesheet, report his actual work and also
the remaining work for each taks. In the final step, in 'My Tasks' the
resource will be able to import the relevant timesheet and all the tasks data
will be imported (without the need to enter the remaining work in 'My Tasks'
screen for each task - which can be 15-20 tasks per week).
The purpose of this option is that the resource will need to enter data only
in the 'Timesheets' section and not in 2 places.
Thanks in advance for any help on this,
Regards,
Shai
I am using MSP 2007 server, and this question regards the PWA.
I want the resource to report on his weekly tasks progress only using his
timesheet in the PWA - and then all his tasks will be updated in the Project
- is it possible?
Second option:
I want to add the field 'Remaining Work' to my Timesheet. In this way the
resource will add his tasks to the timesheet, report his actual work and also
the remaining work for each taks. In the final step, in 'My Tasks' the
resource will be able to import the relevant timesheet and all the tasks data
will be imported (without the need to enter the remaining work in 'My Tasks'
screen for each task - which can be 15-20 tasks per week).
The purpose of this option is that the resource will need to enter data only
in the 'Timesheets' section and not in 2 places.
Thanks in advance for any help on this,
Regards,
Shai