Add resource without affecting existing allocations or time

J

Jena

Hi -
I have a task that is schedueld for 8 hrs per week for the next 6 weeks,
with 2 resources allocated at approx 14% of their 6 hrs /day time. The
manager wants to have addtional people helping with this task, but not change
the allocation of the original two. The actual work will generally exceed
the original 8 hrs, but the manager does not want that "plan" to change, she
wants to track actuals against it. How do I add the resource without the
work or duration changing for the originals?
Thanks,
Jena
 
J

Jack Dahlgren MVP

Double click the task to bring up the task information dialog box. On the
"Advanced" tab, make sure that the "Effort Driven" option is NOT selected.
Now assign the other resources. The original assignments should not change.

-Jack Dahlgren
 
J

Jena

Thank you -- When I assigned the addtional resource, I also had to delete
the hours that were allocated for her beyond the actual hours she spent. But
it worked.
Jena
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top