Hi -
I have a task that is schedueld for 8 hrs per week for the next 6 weeks,
with 2 resources allocated at approx 14% of their 6 hrs /day time. The
manager wants to have addtional people helping with this task, but not change
the allocation of the original two. The actual work will generally exceed
the original 8 hrs, but the manager does not want that "plan" to change, she
wants to track actuals against it. How do I add the resource without the
work or duration changing for the originals?
Thanks,
Jena
I have a task that is schedueld for 8 hrs per week for the next 6 weeks,
with 2 resources allocated at approx 14% of their 6 hrs /day time. The
manager wants to have addtional people helping with this task, but not change
the allocation of the original two. The actual work will generally exceed
the original 8 hrs, but the manager does not want that "plan" to change, she
wants to track actuals against it. How do I add the resource without the
work or duration changing for the originals?
Thanks,
Jena