F
Franzi
Hi,
I am putting together a production plan for our shipyard. Currently there
are two 40m+ projects running.
One has just started, the other one is half way completed.
I have made two project plans and then combined them into a masterplan.
Now I am assigning resources from a seperate file which I use only as
resource pool.
Within this resource pool, I have, for example, a resource called
laminators. At the start of the task of laminating my hullshell I have 5 guys
working. So I have set the max number of units for this resource to 500%.
3 weeks into this task I may employ another 8 guys to speed things up on
this task running.
First question is, within the resource pool, to what do I set the max
resource units? To the maximum of laminators I will eventually have (=1300%)?
This way I will not get a resource overallocation once I assign up to 13
workers, BUT, I would equally not get an overallocation warning if I
accidentally assign more then the 5 laminators which I actually have at the
start to other tasks. The latter can easily happen on aproject with several
hundred tasks.
Second question is, within my project masterplan, how do I best show the
increase of people over the running task?
Currently I have worked around it by splitting the task in two, assigning
500% of the resource laminators to this first part of the task and then
assigning 1300% to the second task of the task. Probably there is amore
elegant way to do this?
Thanks for answers in plain english, I'm still along way from becoming a
project guru ;-)
All the best,
Franziska
I am putting together a production plan for our shipyard. Currently there
are two 40m+ projects running.
One has just started, the other one is half way completed.
I have made two project plans and then combined them into a masterplan.
Now I am assigning resources from a seperate file which I use only as
resource pool.
Within this resource pool, I have, for example, a resource called
laminators. At the start of the task of laminating my hullshell I have 5 guys
working. So I have set the max number of units for this resource to 500%.
3 weeks into this task I may employ another 8 guys to speed things up on
this task running.
First question is, within the resource pool, to what do I set the max
resource units? To the maximum of laminators I will eventually have (=1300%)?
This way I will not get a resource overallocation once I assign up to 13
workers, BUT, I would equally not get an overallocation warning if I
accidentally assign more then the 5 laminators which I actually have at the
start to other tasks. The latter can easily happen on aproject with several
hundred tasks.
Second question is, within my project masterplan, how do I best show the
increase of people over the running task?
Currently I have worked around it by splitting the task in two, assigning
500% of the resource laminators to this first part of the task and then
assigning 1300% to the second task of the task. Probably there is amore
elegant way to do this?
Thanks for answers in plain english, I'm still along way from becoming a
project guru ;-)
All the best,
Franziska