Hi,
I try to create a portfolio analyzer view where work and costs can be
considered in relationship to different properties.
On property is a financel controlling number that is assigned each task. I
added a task outlinecode to the enterprise global with the used numbers and
assigned the numbers to the tasks. But this outline code doesn't appear in
the field list when I build the portfolio analyser view. Since ressource
outline codes appear, I guess that only project and ressource field can be
used. So I used a ressource outline code for the controlling numbers and
assigned them in an ressource assignment view to the ressources.
Now I have the numbers in the field list and can use them. But I don't like
this solution, the controlling number is assigned severl times if a task has
more than one ressource and I just don't like assigning a task value in a
ressource field. Is there any other possibilty?
Thanks
Thea
I try to create a portfolio analyzer view where work and costs can be
considered in relationship to different properties.
On property is a financel controlling number that is assigned each task. I
added a task outlinecode to the enterprise global with the used numbers and
assigned the numbers to the tasks. But this outline code doesn't appear in
the field list when I build the portfolio analyser view. Since ressource
outline codes appear, I guess that only project and ressource field can be
used. So I used a ressource outline code for the controlling numbers and
assigned them in an ressource assignment view to the ressources.
Now I have the numbers in the field list and can use them. But I don't like
this solution, the controlling number is assigned severl times if a task has
more than one ressource and I just don't like assigning a task value in a
ressource field. Is there any other possibilty?
Thanks