M
Mike
I have a project with a wide range of dates. I have one
certain task, that if moved to a later date, I want to add
time to other tasks. ie, if the task starts 30 days later,
i want to add 30 days to specific tasks, not change their
start dates, but add a "buffer". I"m not sure how to link
these tasks, if it's possible to do. I hope I was able to
get my problem across. Thanks for your time.
Mike
certain task, that if moved to a later date, I want to add
time to other tasks. ie, if the task starts 30 days later,
i want to add 30 days to specific tasks, not change their
start dates, but add a "buffer". I"m not sure how to link
these tasks, if it's possible to do. I hope I was able to
get my problem across. Thanks for your time.
Mike