Perhaps you better explain what you mean by "working days".
23 Feb 09 -> 6 Mar 09
is a span of 11 TOTAL days. Which day isn't worked?
If you mean to exclude Saturdays and Sundays:
A1: 23 Feb 09
A2: =WORKDAY(A1,10)
will return 9 Mar 09 in A2.