Can anybody give some code samples to add a resource to paricular using
Visual Studio .net.

Thanks in advance
Best Regards
Ihsan
 
I

Ihsan

HI..

i manage to solve that problem .
i am posting my sample code here

'Adding resources to a project
Dim project As Project = appclass.ActiveProject

' appclass.ViewApply()
project.Resources.Add("A", 1)
project.Resources.Add("B", 2)
project.Resources.Add("C", 3)
project.Resources.Add("D", 4)


Dim task As Task = project.Tasks.Add("Requirment Collection")
task.Start = "08/1/2007"
task.Finish = "10/25/2007"

'Assigning a resources to a particular tasks
task.Assignments.Add(task.ID, 1)
task.Assignments.Add(task.ID, 2)
task.Assignments.Add(task.ID, 3)

Thanks Again.

Best Regards
Ihsan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top