D
Daniel
When assigning a resource on a task with work=0h, the cost on this task is
the same that if the setting was work=1h. Is it a bug?
I know it sounds odd to set the work to 0h but some PMs have done it during
a trial and error process for some tasks and now the project total cost is
wrong.
Does it means it’s something not allowed?
Daniel
the same that if the setting was work=1h. Is it a bug?
I know it sounds odd to set the work to 0h but some PMs have done it during
a trial and error process for some tasks and now the project total cost is
wrong.
Does it means it’s something not allowed?
Daniel