Is there any way to add the Baseline Finish to the My Tasks view in Project
Server 2007? It is not in the available columns field.
 
A

Andrew Lavinsky

Try creating an Enterprise Field, set it to equal Baseline Finish, and roll
down to the assignment level. Republish and see if that works.

Note that on some pre-SP2 environments, I have had an issue where once a
formula is set, the roll down option is not available. The work around,
best I can tell in that scenario, is to upgrade, or to add a macro to Project
to copy the data in the file, then publish.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
G

Gary L. Chefetz

What is your patch level? It's available on my servers, which are patched to
current levels.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top