R
Richard.Natividad
Question:
This is a question that I wonder you've come across?
I have some workplans that have Contingency included in their plans.
I have created a custom report that displays EACs and ETCs by month.
However, if a workplan has a contingency task that runs for the length
of the plan it shows up and skews the ETCs. This is visible when I
drag down the Resource column it shows the ETCs for the Contingency
tasks.
Basically is there some way we can put in contingency into the plan
without it skewing the total ETC for the report?
Regards,
Richard
This is a question that I wonder you've come across?
I have some workplans that have Contingency included in their plans.
I have created a custom report that displays EACs and ETCs by month.
However, if a workplan has a contingency task that runs for the length
of the plan it shows up and skews the ETCs. This is visible when I
drag down the Resource column it shows the ETCs for the Contingency
tasks.
Basically is there some way we can put in contingency into the plan
without it skewing the total ETC for the report?
Regards,
Richard