Mark,
Yes however only certain fields in Project will "word wrap". Generally
text based fields (e.g. Task Name, Notes, TextX, etc.) will wrap but
unlike other Microsoft applications the operation is not called "word"
or "text" wrap in Project. In Project the operation is called "row
height" which can be found under View/Table/More Tables. For the
particular table associated with the view being used, hit "edit". In the
lower right of the Table Definition window is a row height selection
box. Set it for "2" or more to accomodate long text.
With Project 2000 and later, you can also individually adjust the height
of each row and thus enable "word wrap". To find out more about this
feature, go to the help file and search for "row height".
Hope this helps.
John