R
Robert
Hi all,
I have created a custom duration1. Duration1 is 25% of
duration. Duration2=125%
Example:
Duration= 10 days
Duration1=Duration/4 = 2,5 days
Duration2=Duration+(Duration/4)=12,5 days
I have a startdate 1st May 2006, Finish 12th May 2006
(i.e. 10 days including a weekend)
What I like to do is add those 2,5 days onto finish date
(or 12,5 days onto the start date) showing up on the Gantt
bar chart aswell.
Adding duration2 (12,5 days) onto start date (logical
enough) gives me a finish1 date of 04-10-2022 *lol*
Adding Duration1 (2,5 days) onto finish date gives finish2
date of 15-10-2022
Any ideas, hints or tips there???
Thanks in advance
Robert
I have created a custom duration1. Duration1 is 25% of
duration. Duration2=125%
Example:
Duration= 10 days
Duration1=Duration/4 = 2,5 days
Duration2=Duration+(Duration/4)=12,5 days
I have a startdate 1st May 2006, Finish 12th May 2006
(i.e. 10 days including a weekend)
What I like to do is add those 2,5 days onto finish date
(or 12,5 days onto the start date) showing up on the Gantt
bar chart aswell.
Adding duration2 (12,5 days) onto start date (logical
enough) gives me a finish1 date of 04-10-2022 *lol*
Adding Duration1 (2,5 days) onto finish date gives finish2
date of 15-10-2022
Any ideas, hints or tips there???
Thanks in advance
Robert