Am using project to plot a one line schedule using multiple start and finish
dates. Example: start1, start2, start3, etc. Not all the start dates run at
the same cadence. Would like to plot a trend line through the start dates to
highlight the different slopes of the cadence lines. Is this possible?

My understanding is that the progress line can be used, but only if the
start id is used. And this only offers 1 line. Any ideas?

Screen shots available if needed.
 
J

Jim Aksel

You may have better success exporting (or copying) the needed data to Excel.
Excel has much better graphics capability.

I do not have a direct solution for you in Project.
--
If this post was helpful, please consider rating it.

Jim

Check out my new blog for more information:
http://www.msprojectblog.com
 
C

colin919

That's what I was afraid of. At the moment am PDF-ing the file and drawing on
it. Was hopeful for a quicker fix. Mark it down as a suggetion for MS.
 