We use project server 2002
is there any way to rename the existing nonproject time
entries and add few more in project server 2002. all our
enterprise resources are at 75% allocation per day ie
just 6 hours of project time the rest of two hours are
divided into admin, production support, meetings,
assisting users, peer review of migrations etc.
We were thinking of of somehow using nonproject time
entries to show the remaining two hours of time (per day )
which a resource usually spends in meetings or doing
production support. so we need to add more entires in the
non project time list
we are hoping that resouces will enter the actual hours
in these nonproject time
entries thus providing a actual hours that we spend on
each day
the main reason is to get this done is as the higher
managment wants to know what the resources are doing when
not working on projects
many thanks in advance
is there any way to rename the existing nonproject time
entries and add few more in project server 2002. all our
enterprise resources are at 75% allocation per day ie
just 6 hours of project time the rest of two hours are
divided into admin, production support, meetings,
assisting users, peer review of migrations etc.
We were thinking of of somehow using nonproject time
entries to show the remaining two hours of time (per day )
which a resource usually spends in meetings or doing
production support. so we need to add more entires in the
non project time list
we are hoping that resouces will enter the actual hours
in these nonproject time
entries thus providing a actual hours that we spend on
each day
the main reason is to get this done is as the higher
managment wants to know what the resources are doing when
not working on projects
many thanks in advance