Adding new tasks always has constrant "Start No Earlier Than" - W

T

Tim

I am using MS Project 2007 and every time I insert a new task it has a
constrant of Start no earlier than on it. I have to go and remove each one.
Why does it do that and is there a profile to stop it?
Thanks
 
J

JulieS

Hi Tim,

Double check your settings in Tools > Options, Schedule tab. Most
likely the option "New tasks" is set to "Start on Current date"
rather than "Project start date".

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
T

Tim

That's it, thanks

JulieS said:
Hi Tim,

Double check your settings in Tools > Options, Schedule tab. Most
likely the option "New tasks" is set to "Start on Current date"
rather than "Project start date".

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 