H
Hawk
Hi- I have found your forum very helpful in my new job, but I'm in need of
some help. Here's my situation: i need to add several tasks to an already
baselined plan. I want to add them to the bottom of the project plan so that
i can accurately track all new tasks, but want them to link back to a
different 'summary' task so that i can see how the new tasks affect the %
complete of the previously baselined summary task (even though the 'summary'
task isn't located directly above the newly inserted tasks).
thoughts?
some help. Here's my situation: i need to add several tasks to an already
baselined plan. I want to add them to the bottom of the project plan so that
i can accurately track all new tasks, but want them to link back to a
different 'summary' task so that i can see how the new tasks affect the %
complete of the previously baselined summary task (even though the 'summary'
task isn't located directly above the newly inserted tasks).
thoughts?