A
Amy
I have a master project plan with mostly strawman plans for future releases
and a few inserted, detailed project plans. After having this plan for a
while, I decided I need to go to a resource pool so I could see which
projects they were assigned to (could only see summary tasks) in resource
usage view.
I created a resource pool by making a copy of the master plan and deleting
the tasks. I told everyone to connect to it for their subplans. Today when
I opened my master plan, all the resource assignments were gone from the
tasks. If I look at the resource pool file, you still see them assigned to
the tasks in that plan in the usage view (as there are no native tasks in the
resource pool file).
What did I do wrong? What happened to my resources on invidviudal tasks in
the master file? Was it becuase I switched to a resource pool mid-plan? I
did not delete the master plan resources, I just changed the option to point
it to the resource pool file.
I am using Office 2007.
and a few inserted, detailed project plans. After having this plan for a
while, I decided I need to go to a resource pool so I could see which
projects they were assigned to (could only see summary tasks) in resource
usage view.
I created a resource pool by making a copy of the master plan and deleting
the tasks. I told everyone to connect to it for their subplans. Today when
I opened my master plan, all the resource assignments were gone from the
tasks. If I look at the resource pool file, you still see them assigned to
the tasks in that plan in the usage view (as there are no native tasks in the
resource pool file).
What did I do wrong? What happened to my resources on invidviudal tasks in
the master file? Was it becuase I switched to a resource pool mid-plan? I
did not delete the master plan resources, I just changed the option to point
it to the resource pool file.
I am using Office 2007.