J
JNB
Hi all,
I create the following task:
Duration: 5 days, Type: Fixed-duration
Effort-driven scheduling: Yes
Initial resource assignment:
Resource #1, 50% Project calculates 20h of work
Resource #2, 50% Project calculates 20h of work
Suppose I decided to increase the total work on the task by assigning
additonal
resources. When I try to assign another resource with 50% of assignment
units, I get the warning message:
"Project cannot create an assignment with a specific unit value on a fixed
duration,
effort-driven task. Once the assignment is created, you can edit the unit
value on
the assignment"
On the other hand, it works if I assign Resource #3 with 100%, adding an
extra 40h of work; then I change it to 50%.
It also works if I enter 20h into the Work field for Resource #3; Project
calculates Units as 50%.
Alternatively, I can turn effort-driven option off, assign the resource and
then
turn it on back.
My purpose is not to find a workaround or define the task with the right
task type
(probably fixed work), instead I just want to understand how it works.
Why do I get the warning message ?
I am sure Project's behaviour is consistent with scheduling algorithm but I
need
some help with figuring out what the logic behind is. Thanks in advance for
any insight.
I create the following task:
Duration: 5 days, Type: Fixed-duration
Effort-driven scheduling: Yes
Initial resource assignment:
Resource #1, 50% Project calculates 20h of work
Resource #2, 50% Project calculates 20h of work
Suppose I decided to increase the total work on the task by assigning
additonal
resources. When I try to assign another resource with 50% of assignment
units, I get the warning message:
"Project cannot create an assignment with a specific unit value on a fixed
duration,
effort-driven task. Once the assignment is created, you can edit the unit
value on
the assignment"
On the other hand, it works if I assign Resource #3 with 100%, adding an
extra 40h of work; then I change it to 50%.
It also works if I enter 20h into the Work field for Resource #3; Project
calculates Units as 50%.
Alternatively, I can turn effort-driven option off, assign the resource and
then
turn it on back.
My purpose is not to find a workaround or define the task with the right
task type
(probably fixed work), instead I just want to understand how it works.
Why do I get the warning message ?
I am sure Project's behaviour is consistent with scheduling algorithm but I
need
some help with figuring out what the logic behind is. Thanks in advance for
any insight.