Adding resources to multiple plans

K

Karen

Hi,

When adding a resource to multiple plans from a global resource pool, I am
currently opening each plan, adding the resource from Global Resource Pool
and assigning to tasks. Is there a way to do this the other way around and
open the resource and select which projects to add the resource to? That
would be really helpful

Thanks
 
C

Chris Marriott

Karen

Sorry no ....

The plan needs to pull in the resource .. there is no push resource into
plan facility


--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 