Hi all, i have a question.

It seem that every language has its own standard calendar
(not sure if it is project calendar).

How do i add in the standard calendar for japanese in
microsoft project server?

Thanks
 
D

Dale Howard

Kimhui --

Log into Project Server in Microsoft Project 2002 Professional using an
account that has Administrator permissions. Open the Enterprise Global.
Click Tools - Change Working Time. In this dialog box, you should see a
calendar listed at the top called "Standard" in whatever language you are
using. This is the default calendar for all new projects and for all new
resources. To make this Standard calendar display the company's schedule,
simply mark any non-working time periods as such. These non-working time
periods would be company holidays and the like. When finished, click OK,
and then save and close the Enterprise Global. Changes made to this
Standard calendar will then adjust the schedule of every project the next
time it is opened. Hope this helps.
 
K

Kimhui

Thanks Dale.
Can you do me a favour by reading a file call psread10.htm.
This file contain some information about "standard
calendar" which i am not very sure about.
It seem that in order for a japanese client to connect to
an english server, the server need to have a "standard
japanese calendar".
The file can be found on the computer that contain the
server. Please help me thank you.
 