Adding Summary Tasks to a Report

N

NancyD

I would like to add the Summary Tasks to the "To-do List" Report in Project 2000. The option to add "summary tasks" is greyed out in the report. Can anyone help
Thank
Nancy
 
M

Mike Glen

Hi Namcy,

Welcome to this Microsoft Project newsgroup :)

Well, summary tasks should not contain resources so there is nothing to do!
It might be possible to write a vba procedure to do what you want,try
posting on the developer newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 