How can I add a task if parent task is having constraint using PSI? I am
getting CorrelationBlocked error in this case.

I am able to add child task successfully if parent task is not having any
constraint.

Thanks & Regards,
Virsharma
 
V

virsharma

I found a way for this … If we remove the resources from the summary task the
child tasks gets successfully added.

Regards,
virsharma
 