Mike
Question for the 2003 experts.
I'm finding a strange issue, if I add timesheets to an existing project on a
fixed work task - It seems that Project then recalculates the work field. Is
there anything specific that would cause this? (It's also modifying
duration, but that's ok)
If I want to add Timephased data/Timesheets to a project, is there anything
I should be careful about touching/not touching? Does MSP store data in the
MSP_Timephased table that could cause problems if I delete and repopulate the
table with timeshoot rows of my own?
I'm finding a strange issue, if I add timesheets to an existing project on a
fixed work task - It seems that Project then recalculates the work field. Is
there anything specific that would cause this? (It's also modifying
duration, but that's ok)
If I want to add Timephased data/Timesheets to a project, is there anything
I should be careful about touching/not touching? Does MSP store data in the
MSP_Timephased table that could cause problems if I delete and repopulate the
table with timeshoot rows of my own?