P
prashanth.sharangapani
Dear MPP users,
I need one help. I use project 2003.
I have one schedule already baselined. However, at the time of
baselining, I had forgot to update the resources charge rate and it
remained as $0. Now I have begun tracking the schedule, but SPI never
shows up because BCWP is $0. I can go and re-baseline, but that will
over write the previous baseline data (my first week of tracking
indicates that we are doing very well on CPI, if I re-baseline, I will
lose that!).
Any idea on how to get around this?
Thanks for the help.
Prashanth
Bangalore, India
I need one help. I use project 2003.
I have one schedule already baselined. However, at the time of
baselining, I had forgot to update the resources charge rate and it
remained as $0. Now I have begun tracking the schedule, but SPI never
shows up because BCWP is $0. I can go and re-baseline, but that will
over write the previous baseline data (my first week of tracking
indicates that we are doing very well on CPI, if I re-baseline, I will
lose that!).
Any idea on how to get around this?
Thanks for the help.
Prashanth
Bangalore, India