J
jhdubose
I can select a task an either use Split or Task Information -->
Precedecessors to see all the predecessors for the task. Does anyone know
how to add up all the values for work of the predecessors to see that total
amount of work for the item and all its predecessors. Using summary task is
not an option because I am using summary task to represent component areas
that get summed, but the critical path spans component areas.
Thanks,
jason
Precedecessors to see all the predecessors for the task. Does anyone know
how to add up all the values for work of the predecessors to see that total
amount of work for the item and all its predecessors. Using summary task is
not an option because I am using summary task to represent component areas
that get summed, but the critical path spans component areas.
Thanks,
jason