I had a request to add the WBS to our "View my tasks" timesheet view. I
added the field in PWA. I added the field to the Enterprise Global as a
field to be published. I can see the WBS on a project view, but can not get
it to display on the timesheet view. Am I missing a step, or is this an
invalid field on the timesheet for some reason?

Thanks.
jem
 
M

mark.everett

Jem -

Have you republished a project and then check the Task View? After you
make it a published field and add the field to the view, you must still
republish the projects (all the projects) for them to get the new view
data.

Hope this helps. Best Regards,
Mark Everett
www.quantumpm.com
 
D

Dale Howard [MVP]

jem --

Adding the WBS field to the Enterprise Global will accomplish nothing.
Instead, you must ask your PM's to add this field to the list of published
fields (Tools - Customize - Published Fields) for every project they manage
and then republish the assignments for each of these projects (Collaborate -
Publish - Republish Assignments). This process will "push" the WBS field
data to each user's timesheet in PWA. In addtition, you must also add the
WBS field to the Timesheet view (Admin - Manage Views in PWA). Hope this
helps.
 