Hi guys,
I'm having a problem when adding Working Time Exception for certain
resources such that MS Project kind of automatically recalculates the
existing Actual Work hours. For example, under the Resource Usage of
the affected resources, 8 hours Actual Work becomes 8.07 hours and some
becomes 0. The total Actual Work hours does not change, it's just the
number of Actual Work hours changes between the working days.
FYI, I'm using MS Project 2007. I believe this is caused by some
settings somewhere. However, I'm confused because this problem only
happens for certain resources only.
Would appreciate any help on this. Thank you.
Cheers,
Ted
I'm having a problem when adding Working Time Exception for certain
resources such that MS Project kind of automatically recalculates the
existing Actual Work hours. For example, under the Resource Usage of
the affected resources, 8 hours Actual Work becomes 8.07 hours and some
becomes 0. The total Actual Work hours does not change, it's just the
number of Actual Work hours changes between the working days.
FYI, I'm using MS Project 2007. I believe this is caused by some
settings somewhere. However, I'm confused because this problem only
happens for certain resources only.
Would appreciate any help on this. Thank you.
Cheers,
Ted