Adjust Actuals - Can you use % Work Complete vs. Timesheet Hours

W

Wendy

our company's default task update is % work complete but when I go to adjust
actuals i only get a timesheet view. can you have this display % work
complete instead or is the idea that the project manager update any incorrect
actuals in the schedule instead of using the PWA adjust actuals.
 
M

Marc Soester

Hi Wendy,

You can adjust the % complete under the "Adjust Actuals". All you need to do
is to scroll the "left side" grid and you will see a column called % Wok
Complete. You are able to edit this colum per task for a resource.
I hope this helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top