N
Newbie
Hello,
I'm trying the Adjust Actual feature in Project Server 2003.
I have the Administrator permissions.
In the Tracking settings page, I set the Manage Periods - Allow only PWA
users...
In the Adjust actual page, I can change the Act.Work for administrative
project tasks, but not for project task : the system shouts a loud beep.
What's wrong ? Thanks for help
Newbie
I'm trying the Adjust Actual feature in Project Server 2003.
I have the Administrator permissions.
In the Tracking settings page, I set the Manage Periods - Allow only PWA
users...
In the Adjust actual page, I can change the Act.Work for administrative
project tasks, but not for project task : the system shouts a loud beep.
What's wrong ? Thanks for help
Newbie