J
JohnJ
Project Server 2003 as a great new feature that provides for actual work to
be protected. However, since we converted our data (4 months ago) much of
the older data that was converted is protected. We need to make some
corrections to the older data. We can't use the "adjust actuals" feature to
modify this information because the first available payperiod was setup as
the conversion date.
How can I make adjustments to older data that is protected?
Thank you,
be protected. However, since we converted our data (4 months ago) much of
the older data that was converted is protected. We need to make some
corrections to the older data. We can't use the "adjust actuals" feature to
modify this information because the first available payperiod was setup as
the conversion date.
How can I make adjustments to older data that is protected?
Thank you,