Adjust Actuals (Task do not appear using % work complete for updat

W

Wendy

There are no values showing up for me to adjust actuals even though I
published the project and approved the hours for my resources. we are using
% complete - can you not use adjust actuals to update % complete?
 
D

Dale Howard [MVP]

Wendy --

I believe that Adjust Actuals is only available if your organization uses
the Hours of work done per day or per week method of tracking. Sorry.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top