Chris waller
I am trying to use the Adjust Dates button to advance an MS Project 2000;
however there appears to be a problem with some tasks which take place over
the weekend. I have created a calendar which I have called weekend and I have
made Saturday and Sunday the only working days and I have allocated the
appropriate tasks to this calendar. The problem is that when I look on the
Gannt Chart the weekends where there is work have not moved as predicted. I
am sure that I am doing something wrong, but I have only been using Project
for a couple of weeks.
Thanks in advance.
however there appears to be a problem with some tasks which take place over
the weekend. I have created a calendar which I have called weekend and I have
made Saturday and Sunday the only working days and I have allocated the
appropriate tasks to this calendar. The problem is that when I look on the
Gannt Chart the weekends where there is work have not moved as predicted. I
am sure that I am doing something wrong, but I have only been using Project
for a couple of weeks.
Thanks in advance.