Adjust Dates

C

Chris waller

I am trying to use the Adjust Dates button to advance an MS Project 2000;
however there appears to be a problem with some tasks which take place over
the weekend. I have created a calendar which I have called weekend and I have
made Saturday and Sunday the only working days and I have allocated the
appropriate tasks to this calendar. The problem is that when I look on the
Gannt Chart the weekends where there is work have not moved as predicted. I
am sure that I am doing something wrong, but I have only been using Project
for a couple of weeks.
Thanks in advance.
 
J

Jack Dahlgren

Chris,

Take a look at your calendar and make sure the the weekends are there for
each month. Sometimes people make changes which do not go far enough into the
future and don't realize it.

-Jack Dahlgren
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top