B
Brandy
I am on PS2003 and I believe we are current on our patches. I am using
managed periods and users update their actual hours and remaining hours. I
have milestones that are not assigned to anyone. When I go into project to
manually change the progress to 100% when the milestone has been reached, I
get a message that says that acutals may be out of synch and Do you want to
sync the actuals when you save this project. If I DO NOT synch them, the
updates that I made are published and are fine, however, the next time a user
goes in and updates their actuals, when I go to update, I get the same
message and if I select to NOT sync, the users actuals don't get updated
either. What am I doing wrong. In a nutshell, I want the users to update
their own hours and I should be able to update tasks that are assigned to
"non enterprise" resources and update milestones. Please help!
managed periods and users update their actual hours and remaining hours. I
have milestones that are not assigned to anyone. When I go into project to
manually change the progress to 100% when the milestone has been reached, I
get a message that says that acutals may be out of synch and Do you want to
sync the actuals when you save this project. If I DO NOT synch them, the
updates that I made are published and are fine, however, the next time a user
goes in and updates their actuals, when I go to update, I get the same
message and if I select to NOT sync, the users actuals don't get updated
either. What am I doing wrong. In a nutshell, I want the users to update
their own hours and I should be able to update tasks that are assigned to
"non enterprise" resources and update milestones. Please help!