R
reb-clo
Hi
I have been tasked with the fun job of moving some protected actuals from
one plan to another. I have been doing this by using the adjust actuals
feature in PWA, and zeroing the hours in the old plan.
When I have done this, the hours look fine in the new plan. They are logged
as actual work and there is no remaining work. However, in the resource's
timesheet, it shows the hours I moved as being remaining work and no actual
work has been done. I am using Project Server 2003 with PWA.
Does anyone know why this is? They also don't have the option to change
remaining work, but I wish to keep it this way as these are bucket tasks!
Thanks!
I have been tasked with the fun job of moving some protected actuals from
one plan to another. I have been doing this by using the adjust actuals
feature in PWA, and zeroing the hours in the old plan.
When I have done this, the hours look fine in the new plan. They are logged
as actual work and there is no remaining work. However, in the resource's
timesheet, it shows the hours I moved as being remaining work and no actual
work has been done. I am using Project Server 2003 with PWA.
Does anyone know why this is? They also don't have the option to change
remaining work, but I wish to keep it this way as these are bucket tasks!
Thanks!