Adjusting Actuals

G

Gary

In MS Project Web Access 2003 under resources there is an option for
adjusting actuals. Can this be done through the web access and by a resource
or is this permission given to an admin or higher level resource? My real
question is can the actuals be updated by the resource for reporting purposes
or is this not feasable?
 
J

Jonathan Sofer

This is from the administration guide provide by Microsoft and I think will
help you understand this particular features use and capabilities.

Definition:
Adjust Actuals is a category permission that allows a Project Web Access
user to adjust a team member's submitted timesheet entries (actuals). Grant
this permission to any member of your organization who requires the ability
to adjust a resource's timesheet entry.
For example, grant this permission to project managers, resource managers,
and financial managers who need to ensure that the Project Server timesheet
reporting can be synchronized with an external timesheet application like
Siebel.
This permission requires that users:
.. Have permissions to a category or group that also has the View Adjust
Actuals global permission

So this permission can be granted to any user of PWA and is done via PWA.
This is adusting the actuals that are being submitted to the project under
the Updates tab.

Jonathan
 