D
Dave
Hi,
I have a project where the project team is made up of
people from the US (East Coast) and India. As such there
is about a 9 1/2 hour difference in Time Zone. That is,
at 8 AM on Monday US EST, its 5:30 PM Monday in India.
What I was hoping to be able to do was to have to base
calendars to apply to the different resources. Each
calendar would be based on that time zone. That way,
when the resource looked at a task on the project plan,
it would represent the actual time/date in their time
zone and they won't have to worry about any conversions.
Is this possible?
For example, I would like to have a task in the US that
runs from say 8am to 1pm on a Tuesday. Then then next
task (Finish to Start dependent upon first) would be
using an India resource. I would like project to know
the working times and Time Zone impacts of the India
Calendar so that the task would start at 8am Wednesday
India time and show up that way in the project.
Using the SAME calendar for each causes the task to start
at 1PM on Tuesday (EST) which is when the India team is
sleeping. Using a Night Shift type of Calendar for India
doesn't quite work either because everything is still
based on US EST time and therefore would show up as
starting on Tuesday at 10:30PM EST (which equates to 8AM
India time).
Right now, I am basically needing to hardcode constraints
(ie can't start until) to manually account for the
differences when needed.
I would appreciate any thoughts on this.
Thank you,
Dave
I have a project where the project team is made up of
people from the US (East Coast) and India. As such there
is about a 9 1/2 hour difference in Time Zone. That is,
at 8 AM on Monday US EST, its 5:30 PM Monday in India.
What I was hoping to be able to do was to have to base
calendars to apply to the different resources. Each
calendar would be based on that time zone. That way,
when the resource looked at a task on the project plan,
it would represent the actual time/date in their time
zone and they won't have to worry about any conversions.
Is this possible?
For example, I would like to have a task in the US that
runs from say 8am to 1pm on a Tuesday. Then then next
task (Finish to Start dependent upon first) would be
using an India resource. I would like project to know
the working times and Time Zone impacts of the India
Calendar so that the task would start at 8am Wednesday
India time and show up that way in the project.
Using the SAME calendar for each causes the task to start
at 1PM on Tuesday (EST) which is when the India team is
sleeping. Using a Night Shift type of Calendar for India
doesn't quite work either because everything is still
based on US EST time and therefore would show up as
starting on Tuesday at 10:30PM EST (which equates to 8AM
India time).
Right now, I am basically needing to hardcode constraints
(ie can't start until) to manually account for the
differences when needed.
I would appreciate any thoughts on this.
Thank you,
Dave