N
nazdar1
Hello all,
I am using MS project server 2003 with SP1, when user of this server
create a project and when tasks begin late or early, project doesn't
change the task start dates or adjust the remaining portion of tasks.
Calculation Mode is set to automatic and I played with four check boxes
and tried to change this behavior but I have not been able to fix this
problem.
Also customize project web access for Time period setting is set to Non
Managed periods.
Any suggestions appreciated.
Sherry
I am using MS project server 2003 with SP1, when user of this server
create a project and when tasks begin late or early, project doesn't
change the task start dates or adjust the remaining portion of tasks.
Calculation Mode is set to automatic and I played with four check boxes
and tried to change this behavior but I have not been able to fix this
problem.
Also customize project web access for Time period setting is set to Non
Managed periods.
Any suggestions appreciated.
Sherry