I know I can set the project start/end dates, but is there any way to
adust the specific time a project starts without creating a constraint?
I have a project which starts off with the submssion of a change
request which needs to happen at the end of the shift the day before
the change takes place. The resource works until 4 PM daily, the task
needs to start at 3:45 PM and is the first task in the project so its'
only dependency can be the start date of the project.
Any help on this topic would be greatly appreciated.