R
RickH
I've inherited an epm installation and I'm having some problems wit
trying to make changes to some protected actuals in project serve
2003 sp1
We are using timesheets to gather time against tasks and some Actua
Work has appeared against a task in an admin plan, but when you us
Adjust Actuals in PWA there are no values in the timesheet view.
When I look at the Actual Work for the assignment in MS Project usin
the Resource Usage view it looks as if the % complete for tha
assignment has been set to 100% and MS Project has copied t
scheduled work into the actual work fields. Is this possible and ho
do I adjust these actuals
Also ..... my understanding is that protected actuals are only update
through time being submitted on the timesheets in PWA and not directl
through the project plan in MS Project, is this correct ?
Many thank
Richard Harriso
trying to make changes to some protected actuals in project serve
2003 sp1
We are using timesheets to gather time against tasks and some Actua
Work has appeared against a task in an admin plan, but when you us
Adjust Actuals in PWA there are no values in the timesheet view.
When I look at the Actual Work for the assignment in MS Project usin
the Resource Usage view it looks as if the % complete for tha
assignment has been set to 100% and MS Project has copied t
scheduled work into the actual work fields. Is this possible and ho
do I adjust these actuals
Also ..... my understanding is that protected actuals are only update
through time being submitted on the timesheets in PWA and not directl
through the project plan in MS Project, is this correct ?
Many thank
Richard Harriso