C
carpfodder
Scenario:
* Two tasks linked together
* Both tasks have duration of one day
* Summary shows 2 days total duration
* Both tasks have %50 completion
* Adjust first task remaining duration to add one more day
* RESULT:
- first task duration now 2 days (GOOD)
- second task neither moved out nor split to account for longer first task
duration (NOT GOOD)
- Summary still shows 2 days (NOT GOOD)
* DESIRED RESULT
- second task start date is pushed out or second task is split - full
calendar
start/finish represents the entire (newly adjusted) time required for
both
tasks in series
- Summary shows 3 days
Is there a way to have MS Project automatically re-adjust task start/end
dates for all linked tasks when the remaining duration of one changes?
A workaround is...
1. clear the links
2. copy the schedule
3. clear the percent complete,
4. relink
5. paste back the old percent complete column from the copy
This is very time consuming, however.
Thanks.
* Two tasks linked together
* Both tasks have duration of one day
* Summary shows 2 days total duration
* Both tasks have %50 completion
* Adjust first task remaining duration to add one more day
* RESULT:
- first task duration now 2 days (GOOD)
- second task neither moved out nor split to account for longer first task
duration (NOT GOOD)
- Summary still shows 2 days (NOT GOOD)
* DESIRED RESULT
- second task start date is pushed out or second task is split - full
calendar
start/finish represents the entire (newly adjusted) time required for
both
tasks in series
- Summary shows 3 days
Is there a way to have MS Project automatically re-adjust task start/end
dates for all linked tasks when the remaining duration of one changes?
A workaround is...
1. clear the links
2. copy the schedule
3. clear the percent complete,
4. relink
5. paste back the old percent complete column from the copy
This is very time consuming, however.
Thanks.