Dave5000
I am working with some part time help and trying to use resource leveling to
autimatically adjust the end date of a task based on the duration of the work
and the availability of the resource. For example, if the taks takes 10
days, and the resouce can only work 50% of the time, The actual calendar time
to complete the task should become 20 days. I am hoping that project is
capable of determining the end date based on this simple calculation, but
can't seem to get it to do so. Any help would be much appreciated....