M
Mike
Hello all, I really hope I can get some help on this one. I have been
granted the glorious task of implementing MS Project 2003 to our IT
dept of about 85 people. Everything is going fine, we've ran some test
projects with a small group and normal use has been what we expected.
Here's the problem: We are using an administrative project for the
typical stuff (sick, vactaion, personal days, etc). All 85 resources
are assigned to the 6 tasks in the admin project (1 task each for sick
time, vacation time, and 4 others). The problem is happening when we
approving time entered into this admin project. After approving the
time in PWA, of course it opens the project in Project Pro and saves
the project. When doing so, it then blasts email to all 85 resources
alerting them that there was a change in the project. All we did was
approve time. This happens even when it's as little as approving time
for 1 resource into 1 task of the admin project. It's acting as if
it's automatically doing a publish all on save. We've verified that
the checkbox (New and Changed assignments) under Collaborate >
Collaborate Options > Collaborate Tab is NOT checked.
I'm told this should not happen, but regardless, it is. We do not have
this problem with normal projects, only administrative projects. Any
insight in how to resolve this?
Regards,
Mike
granted the glorious task of implementing MS Project 2003 to our IT
dept of about 85 people. Everything is going fine, we've ran some test
projects with a small group and normal use has been what we expected.
Here's the problem: We are using an administrative project for the
typical stuff (sick, vactaion, personal days, etc). All 85 resources
are assigned to the 6 tasks in the admin project (1 task each for sick
time, vacation time, and 4 others). The problem is happening when we
approving time entered into this admin project. After approving the
time in PWA, of course it opens the project in Project Pro and saves
the project. When doing so, it then blasts email to all 85 resources
alerting them that there was a change in the project. All we did was
approve time. This happens even when it's as little as approving time
for 1 resource into 1 task of the admin project. It's acting as if
it's automatically doing a publish all on save. We've verified that
the checkbox (New and Changed assignments) under Collaborate >
Collaborate Options > Collaborate Tab is NOT checked.
I'm told this should not happen, but regardless, it is. We do not have
this problem with normal projects, only administrative projects. Any
insight in how to resolve this?
Regards,
Mike